The Largest U.S. Grid Operator Puts 1,200 Mostly Solar Projects on Hold for Two Years
View
Date:2025-04-15 13:08:35
The nation’s largest electrical grid operator has approved a new process for adding power plants to the sprawling transmission system it manages, including a two-year pause on reviewing and potentially approving some 1,200 projects, mostly solar power, that are part of a controversial backlog.
PJM Interconnection operates a competitive market for wholesale electricity in all or part of 13 states and the District of Columbia, from Virginia to northern Illinois. Its plan is the result of work over the past year by PJM and what it calls its stakeholders, according to a press release from PJM. They include electric utilities, electric transmission owners, state and consumer interests, and solar and wind developers.
“These changes represent a landmark accomplishment for PJM stakeholders and staff that establishes a better process to handle the unprecedented influx of generation interconnection requests and is critical to clearing the backlog of projects,” said PJM President and CEO Manu Asthana.
PJM remains committed to a strategy of “decarbonization policies while preserving reliability and cost-effectiveness,” Asthana said.
But the backlog, and a two-year pause on so many projects with the potential for even longer delays on new proposals, has frustrated a number of renewable energy developers.
In January, an outspoken Adam Edelen, a former Kentucky state auditor who runs a company working to bring solar projects and jobs to ailing coal communities in Appalachia, said he was concerned that “the kink in the system” was helping to delay effective climate policy in the United States. “The planet does not have time for a delay,” he said at the time.
Approval delays were putting solar developers in a financial bind and calling into question the Biden administration’s goal of having a carbon-free electricity grid in just 13 years, he cautioned.
Edelen late Thursday afternoon said he was still reviewing PJM’s announcement, which went out on Thursday.
“The current situation is preventing clean energy projects from coming online and is unsustainable,” said Kat Burnham, a principal of Advanced Energy Economy, a trade group for clean energy businesses that has expressed frustration with the situation. “While the reforms aren’t perfect, the updated process will help mitigate the project backlog. Any further delays would be worse for advanced energy projects and America’s clean energy transition.”
A PJM spokesman, Jeffrey Shields, said PJM would send its plan to the Federal Energy Regulatory Commission in May. FERC has 60 days to act on the plan, or it could not act and the plan would go into effect, Shields said.
Over the last four years, PJM officials have said they have experienced a fundamental shift in the number and type of energy projects seeking to be added to a grid, each needing careful study to ensure reliability. It used to be that PJM would see fewer, but larger, fossil fuel proposals. Now, they are seeing a larger number of smaller, largely renewable energy projects.
In all, there are about 2,500 projects awaiting action by the grid operator, which is based in Valley Forge, Pennsylvania, outside Philadelphia.
PJM has put forward a two-phased solution.
A new approval process will put projects that are the readiest for construction at the front of the line, and discourage those that might be more speculative or that have not secured all their financing.
Then, an interim period will put a two-year delay on about 1,250 projects in their queue—close to half of the total—and defer the review of new projects until the fourth quarter of 2025, with final decisions on those coming as late as the end of 2027.
Shields said that during the two-year transition, PJM will continue to work on more than 1,200 projects, which include more than 100,000 megawatts of renewable energy. “There is no shortage of renewables poised to come online,” he said.
The backlog, caused in part by the explosion of interest in solar energy, varies by state. Earlier this year, there were hundreds of projects waiting for review in states like Pennsylvania and Virginia, and dozens in states like Kentucky and West Virginia.
The Pennsylvania Energy Office was still reviewing the plan, said its spokesman, Jamar Thrasher, on Thursday.
“We support the changes PJM is implementing to create a more efficient and effective process, which will allow for the timely interconnection of generation to the PJM grid while ensuring reliability,” said Tammy Ridout, spokeswoman for the Ohio-based utility AEP.
“These improvements are critical to handle the influx of interconnection requests we have seen in recent years and will see for the foreseeable future,” said Ken Seiler, PJM vice president of planning, in a written statement. “This plan represents a real compromise among many different interests to get renewable and other projects through the queue as fast as possible and give developers a clearer picture of their costs and timelines.”
veryGood! (215)
Related
- Gen. Mark Milley's security detail and security clearance revoked, Pentagon says
- ‘Traitor': After bitter primary, DeSantis may struggle to win over Trump supporters if he runs again
- Powerball winning numbers for January 29 drawing: Jackpot rises to $188 million
- Untangling the Ongoing Feud Between Nicki Minaj and Megan Thee Stallion
- New data highlights 'achievement gap' for students in the US
- Data shows at least 8,500 U.S. schools at greater risk of measles outbreaks as vaccination rates decline
- Beach Boys singer Brian Wilson mourns death of wife Melinda Ledbetter: 'She was my savior'
- Ukraine has improved conditions for its Hungarian minority. It might not be enough for Viktor Orbán
- Bill Belichick's salary at North Carolina: School releases football coach's contract details
- Tropicana Las Vegas, a Sin City landmark since 1957, will be demolished to make way for MLB baseball
Ranking
- Israel lets Palestinians go back to northern Gaza for first time in over a year as cease
- 5 suspects charged with murder in Southern California desert killings in dispute over marijuana
- Groundhog Day’s biggest star is Phil, but the holiday’s deep roots extend well beyond Punxsutawney
- Wisconsin man gets life sentence in 2021 killings of 3 men whose bodies were found outside quarry
- NFL Week 15 picks straight up and against spread: Bills, Lions put No. 1 seed hopes on line
- Tennessee football program, other sports under NCAA investigation for possible NIL violations
- The UAE ambassador takes post in Damascus after nearly 13 years of cut ties
- Poland’s new government asks Germany to think creatively about compensation for World War II losses
Recommendation
Senate begins final push to expand Social Security benefits for millions of people
Data shows at least 8,500 U.S. schools at greater risk of measles outbreaks as vaccination rates decline
Tropicana Las Vegas, a Sin City landmark since 1957, will be demolished to make way for MLB baseball
Best Super Bowl LVIII player prop bets for Chiefs-49ers you can place right now
The company planning a successor to Concorde makes its first supersonic test
Stephen Curry to battle Sabrina Ionescu in first-ever NBA vs. WNBA 3-Point Challenge
Joni Mitchell announces Hollywood Bowl concert, her first LA performance in 24 years
'Riverdale' star Lili Reinhart diagnosed with alopecia amid 'major depressive episode'